Drilling machine operation procedures

1. Before working, it is necessary to comprehensively check whether the operating mechanism of each part is normal, clean the rocker arm guide rail with fine cotton yarn, and inject oil according to the brand of lubricating oil.

2. The operation can only be carried out after the rocker arm and each part of the headstock are locked.

3. There shall be no obstacles within the swing range of the rocker arm.

4. Before drilling, the worktable, workpieces, fixtures and cutting tools of the drilling machine must be aligned and fastened.

5. Select the spindle speed and feed correctly, and do not overload.

6. When drilling beyond the worktable, the workpiece must be stable.

7. When the machine tool is in operation and automatic feed, it is not allowed to change the speed. If the speed is changed, it can only be carried out when the spindle is completely stopped.

8. The loading and unloading of cutting tools and the measurement of workpieces must be carried out during the shutdown. It is not allowed to drill the workpieces directly by hand or wear gloves.

9. If abnormal noise is found in the work, it must be stopped immediately to check and remove the fault.

FX-18CNC-4 High Precision Centerless Grinder

FX-12CNC High Precision Centerless Grinder

FX-18S/AS/BS FX-18HS FX-20S High Precision Centerless Grinder





评论

此博客中的热门博文

Yamazaki Mazak CNC machine tool manufacturer

Brief history of drilling machine development